Skip to content
  • en
  • sv
  • fi
Lounavoima logo

Menu

  • Home
  • News
  • About us
  • Plant
    • Online safety orientation
    • Timeline
  • Environment
    • Development projects
  • Contact
    • Visits
Lounavoima / Plant / Timeline

Timeline

Progress of the waste-to-energy plant project in Korvenmäki

Lounavoima was founded

12/2017

Founded on 4 December 2017, Lounavoima Oy is a local Waste-to-Energy company. Lounavoima is owned by Lounais-Suomen Jätehuolto Oy (50%) and Salon Kaukolämpö Oy (50%).
The company is building a Waste-to-Energy (WtE) combined heat and power (CHP) plant in Korvenmäki, Salo. The plant produces local energy from unrecyclable solid municipal waste.

Petri Onikki begins duties as Managing Director

05/2018

Petri Onikki (MSc Technology, Energy Technology) was appointed Managing Director of Lounavoima Oy. Onikki joined Lounavoima from his duties as Business Development Manager at Fortum. As Managing Director of Lounavoima, Onikki is responsible for launching the young company’s operations and forming its organisation. The most important task in the near future is completion of the WtE plant project, including everything from plant design and construction to its opening.

Environmental permit May 2018

05/2018

On 7 May 2018, the Regional State Administrative Agency (RSAA) issued a positive decision on the environmental permit for the Korvenmäki WtE plant. Receipt of the environmental permit is a major step in the progress of the project. Construction of the plant will begin in accordance with the terms of the permit decision.

Primary plant equipment agreements

01/2019

The project is being carried out on the basis of several tenders in the procurement package. The selection of each component provider will be made in December.

Procurement package 1

  • Grate, steam boiler, turbine
  • Boiler building

Procurement package 2

  • Flue gas treatment process
  • Chimney and heat recovery
  • Flue gas analysers
  • Water plant

Procurement package 3

  • Construction project (waste receiving building, storage bunker, turbine building, visitor centre (incl. office, repair shop, storage)
  • Worksite operations
  • General contractor

Procurement package 4

  • Waste cranes

Earthworks begins

01/2019

Excavation and earthworks, which include roads, connections and foundation work, will begin on the WtE plant site.

Construction begins

03/2019

Building foundation work to begin. The plant will be built adjacent to the existing waste processing centre and in close proximity to Highway 110.

The ground slab for the waste bunker will be laid

05/2019

The slab for the waste bunker will be the largest single pour (by mass) of the entire plant site.

Installation of power and district heating connections

05/2019

A procurement decision will be made concerning installation of the 20 kV underground cable between Korvenmäki and the Ylhäisi power station as well as construction of a district heating pipe from Korvenmäki to the Salo city centre.

The boiler supplier will begin work on the site

10/2019

The delivery of boiler structures and components to the plant site will begin. Component assembly and boiler construction will begin.

The waste cranes will be installed

11/2019

The waste cranes runway beams will be installed in the waste bunker building, followed by installation of the large overhead crane bridges. The waste cranes are used to feed waste into the incinerator.

The flue gas treatment supplier will begin work on the site

12/2019

Preparations for installation of the flue gas scrubbers will begin

Recruiting of plant operational personnel

03/2020

The plant will bring 15-20 new permanent jobs to Salo.

The turbine will be installed

07/2020

Installation of the plant power generation equipment, which converts steam energy into electricity.

The first waste load will be processed

11/2020

The plant will begin receiving waste fuel for test runs. The WtE plant can be reached on Highway 110, using the existing intersection to the Korvenmäki waste processing plant. Waste shipments will arrive on weekdays from 7:00am to 10:00pm.

The first heating of the boiler will be done

11/2020

The WtE plant will begin starting up for operation and the auxiliary burners will be tested for the first time.

The first waste load will be incinerated

03/2021

Waste fuel will be used for the first time as the plant fuel. During the test run, the performance and output of the entire plant will be tested. The commissioning of the plant will last approximately 6 months.

Plant reception

11/2021

After approved test runs, the plant will be transferred to Lounavoima. The plant will produce 90% of Salo’s district heating needs, thus replacing the fossil fuels currently used for Salo’s district heating network.

Follow us on
social media

VISITS

Would you like to visit the plant? Book a time for your group.

Book a visit

INFORMATION ON OPERATIONS

Would you like to know more about the plant operations and its impacts?

Read more about the plant

  • Home
  • News
  • About us
  • Plant
  • Environment
  • Contact

Lounavoima Oy
Helsingintie 541
24100 Salo

Business ID 2875090-3

tiedotus@lounavoima.fi

Privacy policy